Benchmarking#

The list below are the required benchmarking values for Part C#

Target KPIs vs Achieved KPIs#

  • User

  • DGNB

  • CO2/User

  • Cost

BEATS#

  • Total floor area [m2]

  • Office area of permanent workspaces [m2]

  • Number of permanent workspaces

  • Minimum floor-to-ceiling height [m]

  • Total Building height [m]

Environmental Impact#

  • CO2 per workspace ([(CO2*kg/m2/year)*Total office area (m2)] / Permanent desks)

  • Total Embodied CO2

  • CO2 per discipline ( 6 values)

  • Estimated reuse percentage [%] (Approximate percentage of reused materials/components included in the proposal, please explain how you came up with the number)

Cost & Hours#

  • Total hours

  • Hours per discipline ( 6 values)

  • Hourly consultancy rate used for each discipline ( 6 values)

  • Consultancy cost (Discipline hours * Discipline rate) ( 6 values)

  • Estimated Building/Construction cost

    • Arch (e.g. cost of facades, roof, partitions, etc.)

    • Structure (cost of structural systems)

    • Geo (e.g. excavation, foundations, ground improvement work)

    • MEP (cost of MEP systems)

    • Mat (cost of materials and finishes)